Creating WBS means subdividing the major project deliverables into smaller components until the deliverables are defined to the level()
A.independentresource B.individualworkload C.workmilestone D.workpackage
Configuration management system can be used in defining...
Configuration management system can be used in defining approval levels for authorizing changes and providing a method to validate approved changes.()is not a project configuration management tool.
A.RationalClearcase B.QualityFunctionDeployment C.VisualSourceSafe D.ConcurrentVersions System
Changes may be requested by any stakeholder involved wi...
Changes may be requested by any stakeholder involved with the project, but changes can be authorized only by()
A.executive IT manager B.projectmanger C.change control board D.projectsponsor
Many useful tools and techniques are used in developing...
单项选择题Many useful tools and techniques are used in developing schedule()is a schedule network analysis technique that modifies the project schedule to account for limited resource.
A.PERT B.Resourceleveling C.Schedulecompression D.Critical chain method