单项选择题
A、项目经理 B、公司高层领导 C、变更控制委员会 D、公司高层领导与客户方高层领导共同
In project management , a (73) is a listing of a projec...
单项选择题In project management , a (73) is a listing of a project’s milestones, activities, and deliverables, usually with intended start and finish dates. Those items are often estimated in terms of resource (74) ,budget and duration, linked by dependencies and scheduled events.
A. schedule B. activity C. plan D. contractor
Circuit-switching technology is used in Publish Switche...
单项选择题Circuit-switching technology is used in Publish Switched Telephone Network(PSTN), Global System for Mobile Communications(GSM) and code Division Multiple Access (CMDA) . It is a ( ) information transfer mode.
A. connection oriented B. connectionless C. high bandwidth utilization D.poor real-time
Information theory is related to the quantification of ...
单项选择题Information theory is related to the quantification of information. This was developed by Claude E. Shannon to who found fundamental limits on ( ) operations such as compressing data and on reliably storing and communicating data.
A. signal B. data C. information D. signal processing