A.Developing key personnel B.Leading technical specialists C.Interfacing with customers / sponsors D.Analyzing skills
Whydoesaprojectmanagerneedanexecutivesponsor?()A.To kee...
单项选择题Why does a project manager need an executive sponsor?()
A.To keep the project team focused on its work B.To provide behind-the-scenes assistance with organizational commitment and support C.To sign-off on user requirements D.To negotiate contracts with outside vendors
Theprojectmanagerisdevelopingaprojectschedule.Theprojec...
单项选择题The project manager is developing a project schedule. The project manager negotiated with all the execution organizations, and the task times are as short as possible. After manipulating the schedule, the project completion date is still beyond the date requested by the business owners of the project. The project manager believes that the content agreed on for the project is appropriate, and concludes that this schedule should be taken to the business owners and renegotiated. Which one of the following tools will help the project manager justify the revised schedule?()
A.Data flow model B.The project critical path C.Resource loading chart D.WBS (Work Breakdown Structure)
WhatistheMOSTaccuratewaytodetermineaproject’sdurationbe...
单项选择题What is the MOST accurate way to determine a project’s duration before execution?()
A.The project manager performs all estimates B.Incorporate each individual worker’s estimates C.Acquire expert estimates D.There is no way to determine the duration