单项选择题
()is the budgeted amount for the work actually completed on the schedule activity or WBS component during a giving time period.
A.Plannedvalue B.Earned value C.Actualcost D.Costvariance
PDM includes four types of dependencies or precedence r...
PDM includes four types of dependencies or precedence relationships:().The completion ofthe successor activity depends upon the initiation of the predecessor activity.
A.Finish-to-Start B.Finish-to-Finish C.Start-to-Start D.Start-to-Finish
The process of()schedule activity durations uses inform...
The process of()schedule activity durations uses information on schedule activityscope of work, required resource types, estimated resource quantities, and resource calendarswith resource availabilities.
A.estimating B.defining C.planning D.sequencing
The()describes, in detail, the project's deliverables a...
单项选择题The()describes, in detail, the project's deliverables and the work required to create those deliverables.
A.project scope statement B.project requirement C.project charter D.product specification