Companycom has seven days of vmstat data on a p5 590. The server has a total of four test/dev LPARs and 4 production LPARs of one processor each. On the four test/dev LPARs, the data shows 90-95% peak utilizations with a duration of from 5 to 10 minutes. The average utilizations of all LPARs were between 15-30%. All of the applications have different times when they peak. 
What is the best configuration to fully utilize the processor resource?()

A.Set up the server in SMP mode and use WLM to manage resources effectively
B.Set up eight dedicated LPARs and use DLPAR to manage resources effectively
C.Set up a shared pool with eight capped LPARs including production and test/dev
D.Set up a shared pool with eight uncapped LPARs with priority weight to Production