Conducting a project kick-off in the plan phase provides which of the following customer benefits? Select exactly 1 answer(s) from the following:()。

A.ensure that it receives detailed network diagrams
B.reduce the risk of downtime due to facilities-related problems
C.ensure end-user support immediately after the launch of a new system
D.confirm project roles and responsibilities, as well as milestone dates