单项选择题
______ is a method of constructing a project schedule
network diagram that uses boxes or rectangles, referred to as nodes, to
represent activites and connects them with arrows that asow the
dependencies.
This method includes following types of
dependcies orprecedence relationships:
______, the initiation
of the successor activity, depends upon the completion of the predecessor
activity.Estimating activity durations uses information on activity scope of
______, required resource types, estimated resource quantities, and resource
calendars.
A. milestone
B. work
C. quality
D. baseline