单项选择题

______ is a method of constructing a project schedule network diagram that uses boxes or rectangles, referred to as nodes, to represent activites and connects them with arrows that asow the dependencies.
This method includes following types of dependcies orprecedence relationships:
______, the initiation of the successor activity, depends upon the completion of the predecessor activity.Estimating activity durations uses information on activity scope of ______, required resource types, estimated resource quantities, and resource calendars.

A. milestone
B. work
C. quality
D. baseline